When calculating the Critical Path, what happens if two paths have equal duration?单项选择题
A
The project manager ignores one path and tracks only the longest.
B
Both paths are considered critical and must be closely monitored.
C
The path with the least resources becomes critical.
D
The path with discretionary logic is selected as critical.
登录即可查看完整答案
我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。
类似问题
When using Miro to plan a complex project, which capability would you need to obtain from another tool because Miro does not provide it natively?
Question6.2 (0.5 marks) The critical path is [select: , ABCDE, BDE, ACE]. ResetMaximum marks: 0.5 Flag question undefined
There is an activity in the project that has an early start (ES) on day 3, late start (LS) on day 13, early finish (EF) on day 9, and late finish (LF) on day 19. What is the most accurate interpretation of this activity?
"A construction project team develops a detailed network diagram and identifies that the path Foundation ? Framing ? Roofing ? Inspection has zero float and is longer than all other paths. Two weeks into execution, roofing is delayed by 3 days. What is the most direct implication of this delay, assuming no corrective action is taken?"
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!