There is an activity in the project that has an early start (ES) on day 3, late start (LS) on day 13, early finish (EF) on day 9, and late finish (LF) on day 19. What is the most accurate interpretation of this activity?单项选择题

A

The activity has zero float and is therefore on the critical path

B

The activity reflects a scheduling constraint or lag that is affecting its timing

C

The activity indicates negative float and requires immediate schedule compression

D

The activity has a total float of 6 days, indicating it is not on the critical path

E

The activity has a total float of 10 days, indicating it is not on the critical path

登录即可查看完整答案

我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!