"A construction project team develops a detailed network diagram and identifies that the path Foundation ? Framing ? Roofing ? Inspection has zero float and is longer than all other paths. Two weeks into execution, roofing is delayed by 3 days. What is the most direct implication of this delay, assuming no corrective action is taken?"单项选择题

A

Non-critical activities will automatically compress to protect the end date

B

Only roofing activities are affected; project completion date remains unchanged

C

The project completion date is delayed by 3 days

D

The delay can be absorbed by free float on non-critical paths