When calculating the Critical Path, what happens if two paths have equal duration?单项选择题

A

The project manager ignores one path and tracks only the longest.

B

Both paths are considered critical and must be closely monitored.

C

The path with the least resources becomes critical.

D

The path with discretionary logic is selected as critical.