位置14的问题 (Office Move) Consider the following activities: [table] Activity | Description | Immediate predecessor(s) | Activity time (days) T | Find a location | --- | 8 U | Order furniture | T | 6 V | Interview | --- | 4 W | Hire and train | V | 9 X | Remodel | T | 11 Y | Setup furniture | U | 3 Z | Move in | W, X, Y | 1 | | | [/table] Draw the project network. (Office Move) The critical path is ___.T-U-YT-U-ZT-X-ZT-Y-ZV-U-YV-U-ZV-W-YV-W-Z单项选择题

A

T-U-Y

B

T-U-Z

C

T-X-Z

D

T-Y-Z

E

V-U-Y

F

V-U-Z

G

V-W-Y

H

V-W-Z