Question12 How can free float be used to shorten a project schedule?Select one alternative: By finishing the tasks with free floats sooner. By delaying the tasks with free float. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2单项选择题

A

By finishing the tasks with free floats sooner.

B

By delaying the tasks with free float.

C

By assigning free floats to the tasks in critical path to put the pressure off from resources.

D

By reallocating resources from non-critical task with free float to the concurrent tasks in critical path.