Question11 You have recently been assigned as the manager of a highly critical national project which should be finished in a very short period of time compared to the similar projects. After developing the first draft of the project network diagram you see that the project cannot be finished on time. If the network diagram cannot be changed anymore and you have extra human resources, what would be the best approach?Select one alternative: Fast tracking Risk analysis Leveling the resources Crashing ResetMaximum marks: 2单项选择题

A

Fast tracking

B

Risk analysis

C

Leveling the resources

D

Crashing