"A construction project team develops a detailed network diagram and identifies that the path Foundation ? Framing ? Roofing ? Inspection has zero float and is longer than all other paths. Two weeks into execution, roofing is delayed by 3 days. What is the most direct implication of this delay, assuming no corrective action is taken?"Single choice

A

The project completion date is delayed by 3 days

B

The delay can be absorbed by free float on non-critical paths

C

Only roofing activities are affected; project completion date remains unchanged

D

Non-critical activities will automatically compress to protect the end date

Log in for full answers

We've collected over 50,000 authentic original questions and detailed explanations from around the globe. Log in now and get instant access to the answers!

Similar Questions

Part 1Determining the earliest start time​ (ES) and earliest finish time​ (EF) for each activity is known as the​ _______________ through the network. A. slacking B. crashing C. backward pass D. forward pass

Using the activity data below, identify the critical path and the total project duration. Activity                       Duration (Days)                 Predecessors A                                 4                                           - B                                 2                                          A         C                                 4                                          A D                                 2                                          B E                                  5                                         B F                                  3                                         D, E G                                 2                                         F, C H                                 3                                        G I                                   4                                       E J                                  2                                        H, I

"A construction project team develops a detailed network diagram and identifies that the path Foundation ? Framing ? Roofing ? Inspection has zero float and is longer than all other paths. Two weeks into execution, roofing is delayed by 3 days. What is the most direct implication of this delay, assuming no corrective action is taken?"

The critical path is the sequence of schedule activities determining the duration of the project, and is generally the shortest path through the project. 