What is the critical path method based on?单项选择题

A

The assumptions that project activity times cannot be estimated accurately and that they do vary.

B

The assumptions that project activity times can be estimated accurately and that they do not vary.

C

The assumptions that project activity times cannot be estimated accurately and that they do not vary.

登录即可查看完整答案

我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。

类似问题

In CPM method, while only the most realistic time estimate of an activity is the basis for determining the Critical Path, based on the risk-scenario, optimistic and pessimistic time estimations may also be a necessary consideration for evaluating alternative (or what-if) scenarios from a project delivery perspective. 

Part 1Determining the earliest start time​ (ES) and earliest finish time​ (EF) for each activity is known as the​ _______________ through the network. A. slacking B. crashing C. backward pass D. forward pass

Using the activity data below, identify the critical path and the total project duration. Activity                       Duration (Days)                 Predecessors A                                 4                                           - B                                 2                                          A         C                                 4                                          A D                                 2                                          B E                                  5                                         B F                                  3                                         D, E G                                 2                                         F, C H                                 3                                        G I                                   4                                       E J                                  2                                        H, I

"A construction project team develops a detailed network diagram and identifies that the path Foundation ? Framing ? Roofing ? Inspection has zero float and is longer than all other paths. Two weeks into execution, roofing is delayed by 3 days. What is the most direct implication of this delay, assuming no corrective action is taken?"

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!