Part 1Determining the earliest start time (ES) and earliest finish time (EF) for each activity is known as the _______________ through the network. A. slacking B. crashing C. backward pass D. forward pass单项选择题
A
A. slacking
B
B. crashing
C
C. backward pass
D
D. forward pass
登录即可查看完整答案
我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。
类似问题
In CPM method, while only the most realistic time estimate of an activity is the basis for determining the Critical Path, based on the risk-scenario, optimistic and pessimistic time estimations may also be a necessary consideration for evaluating alternative (or what-if) scenarios from a project delivery perspective.
Using the activity data below, identify the critical path and the total project duration. Activity Duration (Days) Predecessors A 4 - B 2 A C 4 A D 2 B E 5 B F 3 D, E G 2 F, C H 3 G I 4 E J 2 H, I
"A construction project team develops a detailed network diagram and identifies that the path Foundation ? Framing ? Roofing ? Inspection has zero float and is longer than all other paths. Two weeks into execution, roofing is delayed by 3 days. What is the most direct implication of this delay, assuming no corrective action is taken?"
"A construction project team develops a detailed network diagram and identifies that the path Foundation ? Framing ? Roofing ? Inspection has zero float and is longer than all other paths. Two weeks into execution, roofing is delayed by 3 days. What is the most direct implication of this delay, assuming no corrective action is taken?"
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!