A major software project is approaching its release date when a critical risk is identified: a key external dependency may not be delivered on time, and the impact could be significant. The project manager reviews available authority and considers several options.Which risk response is most appropriate?单项选择题
A
Ignore the risk unless it happens
B
Add schedule contingency and plan for backup options
C
Escalate the risk to executive management
D
Take all steps to mitigate the impact of external dependency
登录即可查看完整答案
我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!