A project to open a coffee shop has the following activities, durations, and dependencies: A (2 days) → Start B (3 days) → after A C (4 days) → after A D (2 days) → after B E (5 days) → after C F (3 days) → after D and E What is the project duration using the Critical Path Method (CPM)?单项选择题

A

10 days

B

12 days

C

14 days

D

16 days