位置12的问题 (Office Move) Consider the following activities: [table] Activity | Description | Immediate predecessor(s) | Activity time (days) T | Find a location | --- | 8 U | Order furniture | T | 6 V | Interview | --- | 4 W | Hire and train | V | 9 X | Remodel | T | 11 Y | Setup furniture | U | 3 Z | Move in | W, X, Y | 1 | | | [/table] Draw the project network. (Office Move) The latest start time (LST) of activity X is ___.0681016171819单项选择题

A

0

B

6

C

8

D

10

E

16

F

17

G

18

H

19