In "IPD" delivery method, a multi-party contract comprising many specialised parties is signed with the owner as a single agreement. In such agreement, risks and compensations are not assigned to individual stakeholder but rather to the team as a whole on the basis of the overall project performance. Its kind of an alliancing contract. 单项选择题
A
True
B
False
登录即可查看完整答案
我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。
类似问题
One of the integrated project control techniques is "Earned Valued Management (EVM)" where scope, time and cost plans are integrated together to form a single project baseline.
One of the key outputs of the time management plan is the 'schedule control function' which allows monitoring and statusing the project as it proceeds through the construction phase.
In CPM method, while only the most realistic time estimate of an activity is the basis for determining the Critical Path, based on the risk-scenario, optimistic and pessimistic time estimations may also be a necessary consideration for evaluating alternative (or what-if) scenarios from a project delivery perspective.
In activity time estimate, among many factors, the most critical consideration is:
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!