By the virtue of project schedule being one of the key enablers in deliverying the project successfully, the project manager must do the following:单项选择题

A

Follow the schedule as a legal document without fail

B

Analyse schedule risks and communicate the possible eventualities to the key stakeholders for acceptance

C

Analyse and mitigate risks completely

D

Dictate everyone to assess the schedule risks, take stringent corrective actions and follow the baseline schedule as a matter of priority in the project.