By the virtue of project schedule being one of the key enablers in deliverying the project successfully, the project manager must do the following:单项选择题
A
Follow the schedule as a legal document without fail
B
Analyse schedule risks and communicate the possible eventualities to the key stakeholders for acceptance
C
Analyse and mitigate risks completely
D
Dictate everyone to assess the schedule risks, take stringent corrective actions and follow the baseline schedule as a matter of priority in the project.
登录即可查看完整答案
我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。
类似问题
Which of the following covers the three categories of project risk?
One of the integrated project control techniques is "Earned Valued Management (EVM)" where scope, time and cost plans are integrated together to form a single project baseline.
One of the key outputs of the time management plan is the 'schedule control function' which allows monitoring and statusing the project as it proceeds through the construction phase.
In CPM method, while only the most realistic time estimate of an activity is the basis for determining the Critical Path, based on the risk-scenario, optimistic and pessimistic time estimations may also be a necessary consideration for evaluating alternative (or what-if) scenarios from a project delivery perspective.