Using the activity data below, identify the critical path and the total project duration. Activity                       Duration (Days)              Predecessors A                                 4                                       - B                                 2                                       A         C                                 4                                       A D                                 2                                       B E                                  5                                       B F                                  3                                       D, E G                                 2                                        F, C H                                 3                                        G I                                   4                                       E J                                  2                                        H, I 单项选择题

A

Critical Path: A – B – E – F – G – H – J; Project Duration - 21 days

B

Critical Path: A – C – G – H – J; Project Duration - 19 days

C

Critical Path: A – B – D – F – G – H – J; Project Duration - 20 days

D

Critical Path: A – B – E – I – J; Project Duration - 17 days

登录即可查看完整答案

我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!