位置4的问题 (Activity T) Suppose activity T has an earliest start time (EST) of 8, an earliest finish time (EFT) of 13, a latest start time (LST) of 12, and a latest finish time (LFT) of 17. Then, the activity can be STARTED anytime between ___ and ___.8, 128, 1312, 1312, 17单项选择题

A

8, 12

B

8, 13

C

12, 13

D

12, 17