You have been asked to perform a cost-benefit analysis on a new building project in a residential estate. The development company purchased the land for the estate from a farming family 10 years ago. Since then, the company has been trying to get the land rezoned from farming to residential land use. Approval to begin development has just been received. The development company will also provide the energy to the development on an ongoing basis. The company now asks you to provide a cost-benefit analysis to decide whether to proceed with the project, giving you the following information: Item Description Estimated $ value 1 Purchase of farm land $15 million 2 Drainage and sewerage $2 million 3 Construction costs $8 million 4 Sales of houses $27 million 5 Sales from energy annually $1 million Which items are costs and which are benefits to be included in the cost-benefit analysis? Select a single answer.单项选择题

A

Costs: item 3 / Benefits: item 4

B

Costs: items 2, 3 / Benefits: item 4

C

Costs: items 1, 2, 3 / Benefits: items 4, 5

D

Costs: items 2, 3 / Benefits: items 4, 5

E

Costs: items 1, 3 / Benefits: items 4, 5

登录即可查看完整答案

我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!