Question5 As the project manager you are reviewing the earned value analysis (EVA) report performed by your team. The Schedule Performance Index (SPI) is 0.87. What does this figure mean to you?Select one alternative: The project is getting 87 cents out of each dollar spent. Your project is running according to the budget. You are ahead of schedule. The progress of your project is only 87% of what it is planned, so you are behind the schedule. ResetMaximum marks: 2单项选择题

A

The project is getting 87 cents out of each dollar spent.

B

Your project is running according to the budget.

C

You are ahead of schedule.

D

The progress of your project is only 87% of what it is planned, so you are behind the schedule.

登录即可查看完整答案

我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!