A project has a total budget of $800,000 and is planned to be completed in 12 months. After 5 months, half of the budget is spent, and the following data is provided:Planned Value (PV) = $350,000 Earned Value (EV) = $250,000 Remaining Work requires an efficiency factor of 0.9 on the current performance Given this information, calculate the Estimate at Completion (EAC) using the following formula for atypical conditions:EAC=AC+BAC−EVCPI×Efficiency FactorEAC = AC + \frac{BAC - EV}{CPI \times Efficiency \ Factor}单项选择题