Question5 As the project manager you are reviewing the earned value analysis (EVA) report performed by your team. The Schedule Performance Index (SPI) is 0.87. What does this figure mean to you?Select one alternative: The project is getting 87 cents out of each dollar spent. You are ahead of schedule. Your project is running according to the budget. The progress of your project is only 87% of what it is planned, so you are behind the schedule. ResetMaximum marks: 2单项选择题

A

The project is getting 87 cents out of each dollar spent.

B

You are ahead of schedule.

C

Your project is running according to the budget.

D

The progress of your project is only 87% of what it is planned, so you are behind the schedule.