Figure 1. Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 2024) WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC) 2.01 Airframe 48000 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000 45000 2.04 Communications 30000 30000 30000 2.05 Tech. Manuals 42000 42000 48000 2.06 Spares 40000 35000 42000 2.07 Training 80000 80000 86000 Project Total 342000 316000 324000 Consider the project performance report presented in figure 1. What valid conclusion can you draw regarding the project cost performance as of October 31, 2024?单项选择题
A
The project is $8,000 over budget
B
The project is $18,000 over budget
C
The project is on budget
D
The project is $26,000 under budget
登录即可查看完整答案
我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。
类似问题
Why can CPI alone give a misleading picture of project health?
Given CPI < 1 and SPI < 1, and schedule pressure is causing overtime, which EAC formula is MOST realistic?
At Month 4 of a project, PV = $1.2M, EV = $0.95M, and AC = $1.10M. Which interpretation is correct?
Earned Value results show CPI < 1 and SPI < 1. Which conclusion is MOST accurate?
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!