Using the activity data below, identify the critical path and the total project duration. Activity Duration (Days) Predecessors A 4 - B 2 A C 4 A D 2 B E 5 B F 3 D, E G 2 F, C H 3 G I 4 E J 2 H, I 单项选择题
A
Critical Path: A – B – E – F – G – H – J; Project Duration - 21 days
B
Critical Path: A – C – G – H – J; Project Duration - 19 days
C
Critical Path: A – B – D – F – G – H – J; Project Duration - 20 days
D
Critical Path: A – B – E – I – J; Project Duration - 17 days
登录即可查看完整答案
我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。
类似问题
What is the earliest start time (EST) of Activity C?
Question6.1 (0.25 marks for each correct answer. total of 1.5 marks) Activity Aa) Early start time: [input] b) Early finish time: [input] Activity Ca) Early start time: [input] b) Early finish time: [input] Activity Ea) Late start time: [input] b) Late finish time: [input] ResetMaximum marks: 1.5 Flag question undefined [input]
Question6.1 (0.25 marks for each correct answer. total of 1.5 marks) Activity Aa) Early start time: [input] b) Early finish time: [input] Activity Ca) Early start time: [input] b) Early finish time: [input] Activity Ea) Late start time: [input] b) Late finish time: [input] ResetMaximum marks: 1.5 Flag question undefined [input]
Question6.1 (0.25 marks for each correct answer. total of 1.5 marks) Activity Aa) Early start time: [input] b) Early finish time: [input] Activity Ca) Early start time: [input] b) Early finish time: [input] Activity Ea) Late start time: [input] b) Late finish time: [input] ResetMaximum marks: 1.5 Flag question undefined [input]
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!