Part 1Determining the earliest start time​ (ES) and earliest finish time​ (EF) for each activity is known as the​ _______________ through the network. A. slacking B. crashing C. backward pass D. forward pass单项选择题

A

A. slacking

B

B. crashing

C

C. backward pass

D

D. forward pass

登录即可查看完整答案

我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。

类似问题

In CPM method, while only the most realistic time estimate of an activity is the basis for determining the Critical Path, based on the risk-scenario, optimistic and pessimistic time estimations may also be a necessary consideration for evaluating alternative (or what-if) scenarios from a project delivery perspective. 

Using the activity data below, identify the critical path and the total project duration. Activity                       Duration (Days)                 Predecessors A                                 4                                           - B                                 2                                          A         C                                 4                                          A D                                 2                                          B E                                  5                                         B F                                  3                                         D, E G                                 2                                         F, C H                                 3                                        G I                                   4                                       E J                                  2                                        H, I

"A construction project team develops a detailed network diagram and identifies that the path Foundation ? Framing ? Roofing ? Inspection has zero float and is longer than all other paths. Two weeks into execution, roofing is delayed by 3 days. What is the most direct implication of this delay, assuming no corrective action is taken?"

"A construction project team develops a detailed network diagram and identifies that the path Foundation ? Framing ? Roofing ? Inspection has zero float and is longer than all other paths. Two weeks into execution, roofing is delayed by 3 days. What is the most direct implication of this delay, assuming no corrective action is taken?"

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!