During a risk workshop, a tester strongly disagrees with the project manager about the severity of a defect. They debate evidence, challenge assumptions, and agree on a revised risk rating. The relationship remains respectful. How should this conflict be viewedSingle choice

A

Useful task conflict that can improve decision quality

B

Evidence the team lacks any trust

C

Destructive relationship conflict that should be suppressed

D

Administrative conflict about procedures only