During a critical project phase, two senior developers disagree on whether to adopt a new framework or continue using standard tools. The project manager emphasizes the team's shared goals and downplays their differences, encouraging everyone to maintain harmony and move forward without pursuing the conflict further.What conflict management strategy is being used?单项选择题

A

Forcing

B

Avoiding

C

Collaborating

D

Smoothing