Question9 For the purpose of recording project lessons learned, you are analyzing the major delay in the project schedule. The root cause of the delay was a demonstration done by a group of green initiative supporters. They were unhappy because their representatives were not informed about all of the arrangements that you are taking to protect the environment. What could you and your team have done better to prevent this from happening?Select one alternative: A clearer communication management plan A more accurate risk response planning A better project management plan A more accurate stakeholder identification and engagement ResetMaximum marks: 1单项选择题

A

A clearer communication management plan

B

A more accurate risk response planning

C

A better project management plan

D

A more accurate stakeholder identification and engagement