Which of the following statements is FALSE?[Fill in the blank]单项选择题

题目图片
A

a. When you do not have the option to wait, it is optimal to invest in any positive-NPV project.

B

b. One way to see why you sometimes choose not to invest in a positive-NPV project is to think about the decision of when to invest as a choice between two mutually exclusive projects: (1) invest today or (2) wait.

C

c. Real options, and the underlying assets on which they are based, are often traded in competitive markets.

D

d. You invest today only when the NPV of investing today exceeds the value of the option of waiting.