Jenny is working with her team and SMEs to prioritize identified risks for further analysis. They decide to use a five-point scale of very low (VL), low (L), medium (M), high (H), and very high (VH) to assess the likelihood and impact of risk events. This process may be best described as单项选择题

A

Qualitative risk analysis

B

Probability scaling technique

C

Quantitative risk analysis

D

Five-point quantitative assessment