As a project manager, Mary is managing 12 different projects. She realized something very interesting related to them. Sometimes they present some unique and particular rules, like the ones for projects #: 3, 6, and 8. She concluded that neither project 6 nor project 8 is selected unless project 3 is selected.   For integer programming problems, which one of the alternatives listed below correctly models this situation?单项选择题

A

x3 + x6 + x8 ≤ 1

B

x8 ≤ x3, x6 ≤ x3

C

x3 ≤ x8, x3 ≤ x6

D

x6 ≤ x8 , x3 ≤ x8

E

None of the above