1. In the context of reticulated services and construction management, which scenario best demonstrates poor coordination in design management?单项选择题
A
Engaging separate trades for electrical and telecommunications systems with a shared conduit plan.
B
Including electricity connection costs in the project estimate without considering SA Power Networks’ prescribed timelines.
C
Coordinating plumbing and gas installation to ensure a shared trench for cost efficiency.
D
Finalising structural drawings before confirming the required electricity load capacity for the building’s peak operation.
登录即可查看完整答案
我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。
类似问题
If you are a project manager for a building project and you have experience of similar projects in the past, you will be able to draw a reasonable success in such a project by doing the following:
Project Management is simply an extension of Construction Management and thus, to be a good project manager in contruction industry, only skill one must have is "Technical Knowledge of Construction".
Production engineers plan, coordinate, and schedule the manufacturing for structures such as roads, bridges, and skyscrapers.
The colours of the uniforms of the national sports teams of Australia are gold and what other colour?[Fill in the blank]
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!