Let xi = 1 if Project i is selected, i = 1,2,3,4,5; and 0 otherwise: Which answer below indicates that if Project 4 is selected, then Project 2 must also be selected?单项选择题
A
x2 + x4 = 1
B
x2 + x4 ≤ 1
C
x2 ≤ x4
D
x4 ≤ x2
E
None of the above