Which of the following would you do first if you were given the task of conducting the risk analysis for a project ? Choose the most appropriate answer from the options.单项选择题

A

Establish the project risk profile

B

Carry out a qualitative risk assessment

C

Define the project context and scope

D

Carry out a quantitative risk analysis