Broadway Cafe's ERP go-live depends on completing four tasks: clean item master data, configure POS integration, train shift leads, and test inventory updates. Training can occur during testing, but POS integration cannot be tested until item master data is clean. The item master cleanup slips by one week. What is the best project-management conclusion?单项选择题

A

The delay may push the critical path because downstream integration testing depends on clean item data.

B

The delay affects training most because staff cannot learn the system until all testing is complete.

C

The project should switch to Agile because critical paths do not apply to iterative work.

D

Only the cleanup task is delayed because the other tasks can continue independently.