Which of the following statements correctly distinguishes monitoring and controlling activities in predictive versus adaptive projects?单项选择题

A

Predictive projects monitor progress against a fixed baseline, while adaptive projects monitor progress through iterative reviews that adjust scope and priorities as the product evolves.

B

Predictive projects control changes primarily by re-baselining schedules and budgets, while adaptive projects avoid change control because scope is fully defined upfront.

C

Predictive projects rely on timeboxed iterations and frequent customer feedback to control the flow of work while adaptive projects emphasize variance analysis and forecasting.

D

Predictive projects monitor performance only at phase gates, while adaptive projects monitor performance only at the end of each release.