"A government agency launches a three-year initiative to design and implement a new nationwide e-payment system for public services. Once implemented, a separate operations team will run it indefinitely. Which statement best distinguishes project work from operations in this context?"单项选择题

A

Both implementation and ongoing support are projects because they handle technology

B

Implementation and ongoing support are both operations because they are long term

C

Only the initial feasibility study is a project; implementation and operations are both operations

D

"Implementation is a project, while ongoing system support is an operation"