A small parts supplier has three orders waiting to be processed. The shop will begin work today (time = 0). Orders are scheduled using the First-Come, First-Served (FCFS) rule. What are the average days past due and the average flow time for these orders? Customer Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 20 11 8 B 2 6 20 C 10 8 22 单项选择题
A
3.67 days past due; 31 days flow time
B
5.67 days past due; 27 days flow time
C
4.67 days past due; 33 days flow time
D
2.67 days past due; 29 days flow time
登录即可查看完整答案
我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。
类似问题
A Gantt workstation chart shows:
A law office currently has five jobs to be scheduled, shown in the order in which they arrived. Job Processing Time (hours) Due (hours) V 18 24 W 20 35 X 43 46 Y 27 35 Z 55 63 Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using Shortest Processing Time rule.
Which one of the statements concerning sequencing rules is INCORRECT?
Project A has a required return on 9.2 percent and cash flows of −$87,000, $32,600, $35,900, and $43,400 for Years 0 to 3, respectively. Project B has a required return of 12.7 percent and cash flows of −$85,000, $14,700, $21,200, and $89,800 for Years 0 to 3, respectively. Which project(s) should you accept based on net present value if the projects are mutually exclusive?
更多留学生实用工具
希望你的学习变得更简单
加入我们,立即解锁 海量真题 与 独家解析,让复习快人一步!