A small parts supplier has three orders waiting to be processed. The shop will begin work today (time = 0). Orders are scheduled using the First-Come, First-Served (FCFS) rule. What are the average days past due and the average flow time for these orders? Customer Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 20 11 8 B 2 6 20 C 10 8 22  单项选择题

A

3.67 days past due; 31 days flow time

B

5.67 days past due; 27 days flow time

C

4.67 days past due; 33 days flow time

D

2.67 days past due; 29 days flow time