A law office currently has five jobs to be scheduled, shown in the order in which they arrived.   Job Processing Time (hours) Due (hours) V 18 24 W 20 35 X 43 46 Y 27 35 Z 55 63   Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using Shortest Processing Time rule. 单项选择题

A

AFT = 50, AL = 8, ANJ = 4.26

B

AFT = 8.5, AL = 4.26, ANJ = 1.96

C

AFT = 26.3, AL = 12, ANJ = 3.24

D

AFT = 78.4, AL = 39, ANJ = 2.405

E

AFT = 63.6, AL = 27.6, ANJ = 2.16