Part 1The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: [table]
| Copy to Clipboard | | +
[/table] [table]
Activity | Activity Time (days) | Immediate Predecessor(s) A | 66 | long dash— B | 11 | A C | 33 | A D | 33 | B, C
E | 44 | D F | 66 | E G | 55 | E
[/table]Part 2a. Choose the correct network diagram for this project.Part 3
A. StartFinishA6B1C3D3E4F6G5 Edit coordinates (0,0) In the diagram, there are 2 rectangles. The one on the left is labeled Start, and the one on the right is labeled Finish. There are 7 circles labeled inside the circle using the letters from A to G. There is a number below the letter inside each circle. There are arrows that indicate the flows through the circles from Start to Finish as follows: Rectangle Start has an arrow that connects to circle A 6, circle A 6 connects to circle B 1, circle B 1 connects to circle C 3 and to circle D 3, circle C 3 also connects to circle D 3, circle D 3 connects to circle E 4, circle E 4 connects to circle F 6 and to circle G 5, and circles F 6 and G 5 both connect to rectangle Finish. B. StartFinishA6B1C3D3E4F6G5 Edit coordinates (0,0) In the diagram, there are 2 rectangles. The one on the left is labeled Start, and the one on the right is labeled Finish. There are 7 circles labeled inside the circle using the letters from A to G. There is a number below the letter inside each circle. There are arrows that indicate the flows through the circles from Start to Finish as follows: Rectangle Start has an arrow that connects to circle A 6, circle A 6 connects to circle B 1 and to circle C 3, circles B 1 and C 3 connect to circle D 3, circle D 3 connects to circle E 4, circle E 4 connects to circle F 6, circle F 6 connects to circle G 5 and to rectangle Finish, and circle G 5 also connects to rectangle Finish. C. StartFinishA6B1C3D3E4F6G5 Edit coordinates (0,0) In the diagram, there are 2 rectangles. The one on the left is labeled Start, and the one on the right is labeled Finish. There are 7 circles labeled inside the circle using the letters from A to G. There is a number below the letter inside each circle. There are arrows that indicate the flows through the circles from Start to Finish as follows: Rectangle Start has an arrow that connects to circle A 6, circle A 6 connects to circle B 1, circle B 1 connects to circle C 3 and to circle D 3, circle C 3 also connects to circle D 3, circle D 3 connects to circle E 4, circle E 4 connects to circle F 6, circle F 6 connects to circle G 5 and to rectangle Finish, and circle G 5 also connects to rectangle Finish. D. StartFinishA6B1C3D3E4F6G5 Edit coordinates (0,0) In the diagram, there are 2 rectangles. The one on the left is labeled Start, and the one on the right is labeled Finish. There are 7 circles labeled inside the circle using the letters from A to G. There is a number below the letter inside each circle. There are arrows that indicate the flows through the circles from Start to Finish as follows: Rectangle Start has an arrow that connects to circle A 6, circle A 6 connects to circle B 1 and to circle C 3, circles B 1 and C 3 connect to circle D 3, circle D 3 connects to circle E 4, circle E 4 connects to circle F 6 and to circle G 5, and circles F 6 and G 5 both connect to rectangle Finish. Your answer is correct. Part 4b. Determine the critical path and project duration.The critical path is path [input] Upper A dash Upper C dash Upper D dash Upper E dash Upper FA-C-D-E-F Your answer is correct. You answered Upper A dash Upper C dash Upper D dash Upper E dash Upper F. and the project duration is [input]2222 days. (Enter your response as an integer.)Part 5c. Calculate the slack for each activity. (Enter your responses as integers.)[table]
| Slack(days) Activity A | enter your response here B | enter your response here C | enter your response here D | enter your response here E | enter your response here F | enter your response here G | enter your response here
[/table]