Question12 How can free float be used to shorten a project schedule?Select one alternative: By delaying the tasks with free float. By finishing the tasks with free floats sooner. By assigning free floats to the tasks in critical path to put the pressure off from resources. By reallocating resources from non-critical task with free float to the concurrent tasks in critical path. ResetMaximum marks: 2单项选择题

A

By delaying the tasks with free float.

B

By finishing the tasks with free floats sooner.

C

By assigning free floats to the tasks in critical path to put the pressure off from resources.

D

By reallocating resources from non-critical task with free float to the concurrent tasks in critical path.

登录即可查看完整答案

我们收录了全球超50000道真实原题与详细解析,现在登录,立即获得答案。

类似问题

更多留学生实用工具

加入我们,立即解锁 海量真题独家解析,让复习快人一步!