A renewable energy project involves the construction of a solar power plant. The project team is using Monte Carlo simulation for risk modeling. What is the primary benefit of using Monte Carlo simulation in this context?Single choice

Question Image
A

a. Identifying potential environmental impacts of the solar power plant

B

b. Determining the exact number of solar panels needed for the project

C

c. Estimating the probability of achieving the targeted energy output considering uncertainties

D

d. Minimizing the need for maintenance and repair during the operation of the solar power plant

E

e. All of the above