Your team estimates that a new feature will take 3 weeks based on similar past projects. However, halfway through, a key dependency is delayed, and integration takes an extra two weeks. Your manager asks why the estimate was so far off. What was most likely missing from the team’s estimation process?单项选择题

A

Planning poker

B

Accurate story points

C

A Gantt chart

D

Developer time tracking

E

Buffering for uncertainty and external risk